Project:

SOUTH YOLOTEN GAS FIELD DEVELOPMENT 220 kV SWITCHYARD

  • Employer
  • PETROFAC
  • Project Date
  • 2012
  • Project Place
  • Mary - Turkmenistan
  • Project Status
  • Completed
Elektrakom High Voltage Energy Engineering
SOUTH YOLOTEN GAS FIELD DEVELOPMENT 220 kV SWITCHYARD

Design & Engineering of Primary and Secondary Electrical system, Switchyard Civil Design Including all switchyard civil works, Installation of Power Transformers, Installation of Switchyard Materials, Supply of Control / Protection Panels, Supply and Installation of DCS / Telecommunication System, Complete Tests and Commissioning.